15e assemblée générale

de Nant de Drance SA

24 novembre 2023

The history of the power plant

Construction of the Nant de Drance pumped storage power plant took 14 years.

It was a high-altitude, large-scale project, with 18 km of tunnels, 1.7 million m3 of excavated rock, up to 650 workers on site, and an investment of more than CHF 2 billion. The site went into operation in mid-2022.

Best of 2013 to 2022 

The construction story

Feasibility study and blueprint

2003

2007

Atel and the Swiss Federal Railways submit a concession and construction permit application to the Swiss Federal Office of Energy.
Start of work

The Federal Department of the Environment, Transport, Energy and Communications grants the concession and construction permit.

2008

2011

Decision to increase the capacity from 600 to 900 MW
Completion of work to raise the height of the Vieux Emosson.
Dam Completion of power house cavern drilling.

2014

2020

Synchronisation of the first turbine to the extra-high-voltage power grid
Commissioning of the plant

2022

Nant de Drance book

The 14 years of construction of the Nant de Drance power plant.

DISCOVER THE PROJECT HISTORY